May 29

Photos by John Hill

Two trucks carrying the last 4 Azimuth Ring sectors come up the LBT access road. Both the road and the forest are very dry and dusty. The trucks are unloaded with the overhead bridge crane. Each box is lifted with a pair of wire rope slings, and placed on the floor.

May 28

Photos by Jim Slagle

Installing cabinets in the LBT kitchen. Finishing the windows in the control room.
   
The telescope visitor gallery on Level 6.

May 24

Photos by John Hill

View of Firenze from the roof of Arcetri Observatory. Simone Esposito pointing out the Pyramid sensor on the AO test bench.

May 20-21

Photos by John Hill

J. Hill, K. Strassmeier and P. Salinari discuss implementation of the PEPSI instrument on the front porch of Villa Vigoni. The Large Binocular Telescope Corporation Board at work in the Villa Vigoni conference room.
   
The Villa Vigoni in Menaggio, Italy. This meal is up to the standards of the LBT director!

May 16-17

Photos by John Hill

LBT AGW (Acquisition, Guiding and Wavefront) review meeting in Potsdam. Dome of the new library at AIP.

May 13-14

Photos by John Hill

Luciano Miglietta is going to need more help to move this box which contains a section of the Azimuth Frame. Piero Salinari and a freshly painted primary mirror cell.
   
Packing one of the C-Rings in a very large box.

May 8-10

Photos by John Hill

Polishing the first 8.4m primary mirror at the Steward Observatory Mirror Lab. LBT Science Advisory Committee meeting in Bertinoro, Italy.
   
"Bruno's castle" where the SAC meeting was held -- University Residential Centre of Bertinoro
 
 
 
 