The Final Design of the

Large Binocular Telescope

M1 Mirror Cells

L. Miglietta * - P.Gray **

W. Gallieni *** - C. Del Vecchio *

*Osservatorio Astrofisico di Arcetri ** Steward Observatory - University of Arizona

*** ADS Italia - s.r.l.

http://medusa.as.arizona.edu/lbtwww/tech/m1cellhv.htm

Proceedings of SPIE conference on Optical Telescopes of Today and Tomorrow, 2871, 1996

Abstract

1. Interfaces with the main telescope structure

2. Finite Element Analyses of the mirror cell structure

3. The mirror cell geometry and instrument interface

4. M1 mirror support system: pneumatic force actuators and positioning

5. M1 mirror thermal control concept and system plant

6. Details on aluminizing requirements and maintenance

7. Conclusion

8 . References

Abstract

The mirror-cells of the LBT (Large Binocular Telescope) 8.4 m honeycomb borosilicate primary mirrors have to meet various requirements in addition to providing support to the mirrors and to the Gregorian instrumentation. The mirror-cells are directly connected to the main telescope structure and have a structural function themselves in order to supply a very high stiffness boundary to the position actuators (hardpoints) of the primary mirrors. The cells also must guarantee an overall strength to make up the bottom part of the vacuum shell, whose top part is the bell-jar for the mirror aluminizing. Each mirror cell has to hold several components inside: 160 pneumatic actuators for the active optics of the mirror, the thermal control system and its 252 air ejectors, and 6 position actuators. A further requirement for the mirror cell design is also to provide access for the maintenance of all the above sub-systems. In this report we summarize the main mirror-cells functions, their final design and briefly describe how we met all the specifications.

keywords: telescope, primary mirror, actuator support design, thermal control.

1. Interfaces with the main telescope structure

The Mirror Cells are connected to the telescope [1] by the main elevation structures having a C-ring shape and by some lateral trusses to guarantee a stiff lateral supporting as depicted in FIG.1 and FIG.2 . Inside the Mirror Cell are located two longitudinal stiff beams to realize the basic support of the mirror cell to the telescope structure (see FIG. 3): they are directly and stiffly connected to the telescope elevation structure either on the front side or in the back one. Perpendicularly to them other two large beams, and some other smaller, realize the supporting system of the mirror cell floor and the external cylindrical surfaces. The high stiffness required for the Mirror Cell is basically due to two reasons: first we want to support the primary mirrors of the LBT by a structure as stiffer as possible to increase their natural frequencies according to the interferometer requirements of the telescope; then, we need a mirror cell capable to support the mechanical stresses due to the vacuum load during the aluminizing process.

View Figure 1 here

View Figure 2 here

View Figure 3 here

2. Finite Element Analyses of the mirror cell structure

The LBT structure has been analyzed by several numerical simulation studies carried out by finite element analysis in some different boundary conditions [2]; to evaluate separately the influence of the Mirror Cell structure some analyses have been carried out considering it infinitely stiff connected to the telescope frame: a modal analysis, a static analysis under its dead load, with the telescope horizon and zenith pointing, and a static analysis with the external pressure load have been the main analyses performed. In TAB.1 the modal analysis results have been summarized and in FIG.4 the first mode has been depicted. As shown the first eigenfrequency is relatively high, compared with 9 Hz of the telescope structure, and it seems sufficient to avoid any influence on the mirror structure. From a static point of view we have few tenth of millimeter in deformation in both positions (see FIG. 5 and 6), closed to the external diameter, without any influence on the position of the M1 mirror.

Mode Frequency [Hz]
1 18.04
2 19.63
3 27.41
Total mass of the Mirror Cell :
~ 28 tons

TAB.1 - F.E. Modal Analysis of the mirror cell structure

View Figure 4 here

View Figure 5 here

View Figure 6 here

View Figure 7 here

3. The mirror cell geometry and instrument interface

The main mirror cell dimension are depicted in FIG.7 and summarized in TAB.2 . Its total weight, without the M1 mirror and others auxiliary devices, is approximately 28 tons including the bearing system and the cable wrap for the Cassegrain instrumentation. Due to the derotating movement, necessary on the instrument interface, we need to locate a large bearing system, with four points contact balls on the inner 2800 mm diameter, in the central volume of the mirror cell structure. A very high stiffness of this bearing is required either axially or radially with a demanded radial runout less than 0.055 mm.

external flange diameter 8880 mm
internal diameter 8740 mm
central hole 1000 mm
external height 2525 mm
total volume ~ 141 m3
weight of the structure only ~28 tons

TAB. 2 M1 Mirror Cell main data

4. M1 mirror support system: pneumatic force actuators and positioning

ACTUATORS.
The main function of the mirror cell is to support the M1 honeycomb mirror ( external diameter 8.4 m), in such a way that the force of gravity, wind load and telescope acceleration do not deform the surface of the mirror over the specifications data required. In order to oppose the force of gravity in every mirror orientation and to counteract the wind load it is necessary to "float" the mirror by an active actuator network located at the back of the mirror: so the mirror keeps its figure even as the telescope structure bends or flexes under the external loads. All the actuators apply the required force on the backplate of the mirror through glued load spreaders, to avoid local bumps on the mirror surface, in a convenient pattern arranged as discussed in [3]. All the force actuators are pneumatic and can provide fast and accurate regulation of the force but they have very low stiffness. The basic pneumatic actuator model consists of a rolling diaphragm air cylinder with a decoupler on the end so only axial forces are transmitted. The axial load is measured by a load cell, which controls the pressure regulator on the air cylinder. Because of the mirror is not supported at its local center of gravity the axial support forces have to correct the global moment produced when the mirror is horizon pointing. When the telescope is in operation the axial forces are a function of the sine and cosine of the elevation angle and the lateral forces are a function of the sine only: the support vector of a location, every time, is the vector sum of the axial and lateral vectors. The actuators construct this vector sum with two vectors from an actuator pair, which are angled with respect to each other. Therefore the fixed geometry of the actuators can produce a variable direction support vector. Several cross-lateral actuators are provided to balance the mirror in the direction parallel to the elevation axis. The positioning of the mirror in the space is fixed by a system of six positioning actuators (hardpoints) supporting the mirror mass without carrying the gravity load. The mechanical stiffness and the layout of these position actuators affect the resonant frequencies of the M1 mirror supported on the mirror cell. The mechanical tests on these devices have been carried out in the past and in TAB.3 the main performances are summarized with other technical requirements.

System of Force Actuators:
Single Actuators 46
Double Actuators 110
Cross-lateral Actuators 4
160 Total
Directionality: push only or pull only
Nominal Axial Force: -1250 to +1600 N
Nominal Lateral Force: 0 - 1700 N
Measurement Accuracy: 1 / 1200
Measurement Resolution: 1 / 4000
- Operating Pressure Range: 500 - 600 Torr
- Primary compressed air by four feeding lines
System of Position Actuators:
Positioning Actuators 6 ( 3 couples )
Axial static stiffness > 85,000 N/mm
Force Measurement range -300 N to +300 N
" " resolution 0.5 N
Force Breakaway < 3,000 N
- Operating Pressure Range: 3.5 - 4 bar

TAB.3 - M1 mirror cell main data

At 2000 mm from the cell bottom a support grid is located: as shown in FIG.8 all the force actuators and the other thermal devices are placed and fixed on the backside of it. As mentioned above the function of the hardpoints system is to keep the mirror aligned with the other parts of the telescope optical system without applying any force. A load cell is provided in every leg to measure the instant load on it and consequently to correct the axial actuators forces in order to unload the hardpoints. The intrinsic mirror stiffness and the relatively large bandwidth of the actuators response (several Hz) allows for maintaining the mirror figure within specs under most wind conditions encountered on Mt.Graham. A detail study has been carried out on the geometric configuration of the hardpoint legs [4] in order to optimize the support system stiffness and a prototype has been constructed. In our study we basically considered three parameters: the orientation of the legs (V or inverted V assembled), the angle between the legs and the lateral angle of the hardpoints . In the mirror cell layout we have employed a geometric configuration with =100 ° and =15 ° in the external direction where 3 points on the backplate of the mirror (120 ° spaced) are connected to 6 points on the cell floor.

5. M1 mirror thermal control concept and system plant

The M1 borosilicate honeycomb mirror requires a fine temperature conditioning to obtain the required optical performances. The temperature control system has to achieve a mirror mass temperature stability within 0.1 ° C when the external temperature changes 0.25 ° C per hour [5]. The temperature control system adopted in the LBT project is based on static devices, like an ejector, capable to blow control air inside the mirror cell, without any rotating mechanism. Because of the mirror cell works as a plenum overpressured, the air flows from the mirror cell volume right away to the honeycomb mirror cells through some nozzles. To realize this overpressure we employed about 260 air-air ejectors downward oriented (about one ejector for eight mirror nozzles). About 90% of the total air is then recirculated and the 10% is controlled to achieve the required air conditions driving the mirror temperature as the specifications request. Each ejector supplies about 60 g/s by 10,000 Pa difference pressure between the primary and the secondary inlet flow boundary conditions and with about 80 Pa back pressure in the plenum volume. Many experimental tests on the ejector have been carried out in the past to check the global response in different boundary conditions; a more extended discussion on its working performances is in [6]. We can summarize the main qualities of this temperature control system as following: Other secondary phenomena in the mirror cell, as pressure fluctuations and acoustic noise, are negligible in operation conditions. The total required power for each mirror cell is about 48 kW taking into account fans, dehumidifier, dust remover and flow resistance in the air pipeline. In TAB.4 the main parameters of the system are summarized.

Static air conditioning system based on 260 ejectors feeding 1668 single nozzles

Total required air flow rate for the mirror :
~ 14,000 l/s :
~ 12,600 l/s ( 90 % ) ricirculated flow
~ 1,400 l/s ( 10 % ) on line controlled flow
Main thermal control specifications:
Temp. variations in the glass < 0.1 ° C
Temp. differences between mirror
and external ambient air < 0.15 ° C

TAB. 4 - Ventilation and thermal air system for the 8.4 m honeycomb mirror

6. Details on aluminizing requirements and maintenance

One of the innovative concepts adopted in the LBT design is to foreseen the washing and aluminizing processes of the primary mirror in-situ, without remove the M1 mirror off the mirror cell. A vacuum bell-jar is moved to the board of the telescope, by a trolley, and applied on the front of the mirror cell while the telescope is horizon pointing. The F.E.A. of the mirror cell in the aluminizing position, under internal vacuum and external atmospheric pressure submitted, shows that the deformation of the actuator support plane is limited to few millimeters, a value that can easily be accommodated in the range of travel of the actuators. Before the aluminizing phase the pneumatic actuators are evacuated and the mirror rests on the soft pads that limit the actuator range of motion. External seals have to be installed, before aluminizing, to close the cassegrain instrument interface, the cell access door and the ventilation air inlet. On the external edge of the mirror cell a circumferential seal is present to connect it to the bell-jar and a vacuum seal system divides the high vacuum volume (~ 10-6 Torr) from the low vacuum in the mirror cell (~ 10-3 Torr) [7]. An accurate choice of the employed materials in the mirror cell is then required to avoid the outgassing phenomena during the aluminizing phase.

7. Conclusion

The M1 Mirror Cell drawing has been an exciting exercise of mechanical and system design to take into account all the aspects involved in this important substructure of the LBT. As show in TAB. 5 and in FIG.8 there are some crucial components, as the top plate, requiring hi-tech solutions during the manufacturing and assembling processes. After the design phase we are now request to solve the manufactory and testing problems getting the best result with the lowest cost. All the functions requested in the mirror cell specification [8] have been solved by the LBT Project Office and ADS Italia s.r.l. that we wish to thank for their high quality work.

Actuators: 274 holes 100 mm + 114 elliptic slots ( 640 fixing holes 20 mm )
Air ejectors: 260 holes 127 mm ( 780 fixing holes M5 )
Exhausted air sucking pipe: 8 holes 135 mm ( 32 fixing holes M5 )
Shock Absorbers: 327 holes 25 mm ( 1308 fixing holes M5 )
Air Nozzles: 1668 holes f 36 mm
· Total machined slots: 3291
· Total fixing holes M5: 2120

TAB. 5 - M1 mirror cell top plate : total required drillings

View Figure 8 here

8 . References

  1. J.M.Hill - The Large Binocular Telescope Project - Optical Telescopes of Today and Tomorrow - May 29 - June 2, 1996 - Landskrona (Sweden)

  2. C. Del Vecchio, et al. - The Mechanical Structure of the Large Binocular Telescope - Optical Telescopes of Today and Tomorrow - May 29 - June 2, 1996 - Landskrona (Sweden)

  3. G.Parodi, J.M.Hill, P.Salinari - Supporting the 8.4 m Honeycomb Mirrors of Columbus - ESO Conference in Progress in Telescope and Instrumentation Technologies, Garching, April 27-30, 1992

  4. L.Miglietta - M1 Mirror Hardpoints Support System: Modal Analysis in different geometric configurations - Columbus Project Technical Memo OAA-91-04 - Arcetri Technical Report 17- 1991.

  5. A.Y.S.Cheng and J.R.Angel - Thermal Stabilization of Honeycomb Mirrors - Proceedings of ESO Conference on Very Large Telescope and their Instrumentations - March 1988.

  6. L.Miglietta - Primary Mirror Temperature Control System: feasibility study of an air-air ejector device - Columbus Project Technical Memo OAA-91-02 - Arcetri Technical Report 09-1991.

  7. B.A.Sabol, B.Atwood, J.M.Hill, J.T.Williams, M.P.Lesser, P.L.Bayard and W.B.Davison - Evaporative Coating System for Very Large Astronomical Mirrors - Proc. S.P.I.E., 1236,pp 940- 951, 1990.

  8. J.M.Hill - Mirror Support System for Large Honeycomb Mirrors II/R - Large Binocular Telescope Project Technical Memo - UA-95-02