Optomechanics of the Large Binocular Telescope
J. M. Hill
University of Arizona, Large Binocular Telescope Project
Steward Observatory,Tucson, AZ 85721
jhill@as.arizona.edu
P. Salinari
Osservatorio Astrofisico di Arcetri,
Large Binocular Telescope Project
Largo Enrico Fermi 5, 50125 Firenze, ITALY
salinari@arcetri.astro.it
http://medusa.as.arizona.edu/lbtwww/tech/optomech.htm
Proceedings of SPIE conference on Advanced Technology Optical Telescopes V, 2199, p. 64 (1994)
Abstract
1. Introduction
2. Optics
3. Telescope Structure
4. Summary
5. Acknowledgements
6. References
Abstract
We describe the optical layout of the Large Binocular Telescope.
Recent changes in the baseline optical configuration include moving
the wide field foci above the primaries to allow a one degree field at
F/4. The infrared F/15 secondaries are now a Gregorian design to
allow maximum flexibility for adaptive optics. The F/15 secondaries
are undersized to provide a low thermal background focal plane which
is unvignetted over a 4 arcminute diameter field-of-view. The
interferometric focus combining the light from the two 8.4 meter
primaries will reimage two folded Gregorian focal planes to a central
location. The telescope elevation structure accommodates swing arms
which allow rapid interchange of the various secondary and tertiary
mirrors. Using swing arms has allowed us to remove most of the
superstructure supporting the spiders in an earlier version of the
design. Maximum stiffness and minimal thermal disturbance continue to
be important drivers for the detailed design of the telescope. By
concentrating the structural mass between the two elevation C-rings,
we are able to achieve a 2 Hz increase in the lowest eigenfrequency
without increasing the mass of the elevation structure. The telescope
structure accommodates installation of a vacuum bell jar for
aluminizing the primary mirrors in-situ on the telescope. The detailed
design of the telescope structure will be completed during 1994.
1. Introduction
The Large Binocular Telescope (LBT) Project has evolved from concepts
first proposed in 1985. There have been many changes in the LBT over
the past two years. Perhaps most obvious is the change of name ---
the former ``Columbus Project'' has changed its name to the
politically correct ``Large Binocular Telescope''. Other changes
include the configuration of the secondary mirrors and the design of
the optical support structure of the telescope. The technical aspects
of these changes are discussed below.
The partners involved in the design and construction of this 8.4 meter
binocular telescope are the University of Arizona, Italy represented
by the Osservatorio Astronomico di Arcetri and the Research
Corporation based in Tucson. These three partners have committed
sufficient funds to build the enclosure and the telescope populated
with a single 8.4 meter optical train --- approximately 40 million
dollars (1989). Based on this commitment, design and construction
activities are now moving forward. Additional partners are being
sought to provide funding to complete the second optical train of the
binocular and to build facility instruments --- approximately 20
million dollars (1989). We have continued to use 1989 dollars as the
cost basis to reassure our administrations that the scope of the
project has not changed. A reassessment of the costs in current
dollars suggests that the overall project can be accomplished for
approximately 70 million dollars (1994). Just over 8 million dollars
have been spent through the end of 1993.
The telescope configurations shown in Figures 1 and 2 provide a
diffraction baseline of 22.8 meters and a collecting area equivalent
to an 11.8 meter circular aperture. The telescope structure is now in
the phase of final design drawings. The final design of the telescope
is being done by a consortium of ADS Italia (Lecco) and European
Industrial Engineering (Venezia). A contract for architectural
services will be placed shortly to produce the final enclosure design.
The first 8.4 meter honeycomb mirror is next in the queue of the
Steward Observatory Mirror Lab with casting projected for Fall 1995.
Polishing of this mirror should be completed in the Spring of 1998.
The decision to locate the telescope on Mt. Graham was reached at a
relatively early stage. Mt. Graham is over 3200 meters in altitude
and lies in the same Sonoran desert climatic zone as other Arizona
sites such as Kitt Peak and Mt. Hopkins. Seeing measurements have
shown that several sites within the 150 acre Emerald Peak
astrophysical area deliver image quality comparable to the best
recorded at any site. Measurements combined from a Polaris monitor
and microthermal sensors indicate that the median site seeing should
be 0.6 arcsec FWHM if the telescope is mounted above the local
boundary layer at treetop level. In December 1993, with Forest
Service approval, one acre of trees were cut on the LBT site on
Emerald Peak 200 m East of the other two telescopes on Mt. Graham.
Already built are the 10 m submillimeter telescope (SMT) and the 1.8 m
Lennon telescope (VATT) --- both begin science operation in 1994.
2. Optics
2.1 Optical Requirements
The main LBT design drivers from the beginning of the project have been:
- Large total collecting area for sensitivity on faint objects.
- Excellent image quality through passive, active and adaptive
control of seeing and other aberrations.
- Low background from a clean thermal infrared design.
- Versatile instrumentation and rapid changes in configuration to
take maximum advantage of specific observing conditions.
- High ultimate spatial resolution by providing a relatively long
baseline with the stability and field-of-view provided by a common mounting.
- Low construction and operations costs.
The error budget specifies that the telescope and its optics will
produce images to match an r 0 = 45 cm atmosphere. Hill$^1$ reviews
the error budget and detailed performance specifications. This
specification produces an image which is 0.22 arcsec FWHM in the
visible and produces a diffraction-limited image at wavelengths longer
than 2 microns. As the design process moves along, it appears that we
have selected an achievable goal.


The observational priorities which have guided the telescope design
include:
- Interferometric Imaging ............ 0.4 to 400 microns
- Infrared Imaging / Photometry ............ 2.0 to 30 microns
- Wide Field Multiobject Spectroscopy ............ 0.3 to 1.6 microns
- Faint Object / Long Slit Spectroscopy ............ 0.3 to 30 microns
- High Resolution Spectroscopy ............ 0.3 to 30 microns
A representative set of instruments which might be built shortly after
first light include: an optical direct imager, an optical
interferometric imager, a faint object optical spectrograph, a high
resolution optical spectrograph, a near infrared camera, a medium
resolution infrared spectrograph, a thermal infrared imager and
spectrograph. This list is not intended to show any priority order,
nor is it complete, but rather to illustrate the diversity of
observational interests among the community of LBT astronomers.
Provisions for adaptive optics feature prominently in the design of the
telescope.
2.2 Primary Mirrors
From the outset, it was agreed to exploit the borosilicate honeycomb
primary mirror technology because of its relatively simple thermal
control and support characteristics and its prospective lower overall
implementation costs. This technology has now been demonstrated at
the 6.5 m size as described by Olbert et. al. 2. A great deal of our
technical effort over the last four years has gone into understanding
in detail the best practical way to support the 6.5 and 8.4 meter
honeycombs. These blanks are stiffer than other types of mirrors, but
they are still very susceptible to small force errors. Finite element
analysis of the support of these mirrors is described by Parodi, Hill
and Salinari3. We will be supporting the mirrors with active
pneumatic force actuators. A brief description of the mirror support
system is given by Gray et. al. 4. Some results from a similar system
implemented on a 3.5 m mirror are discussed by Martin et. al. 5.
The relevant dimensions of the primary mirrors are:
- Number of Primary Mirrors: 2
- Primary Spacing: 14.417 meters center-to-center
- Primary Glass Diameter: 8.417 meters
- Primary Clear Aperture: 8.408 meters
- Primary Focal Length: 9.600 meters
- Primary Focal Ratio: F/1.142
- Central Hole Glass Diameter: 0.889 meters
% changed to this diameter January 1993
- Central Hole Clear Aperture: 0.898 meters
- Primary Figure: parabolic
- Primary Construction
- cast borosilicate honeycomb
- 28 mm faceplate thickness
- edge thickness 894 mm, plano-concave
- Primary Mirror Mass: approximately 15.6 metric tons each
The 8.4 meter mirrors have a focal ratio of 1.14. This allows
the telescope structure to be very compact, and thus very stiff. The
compact focal ratio also allows us to build a smaller enclosure. The
fast focal ratio requires the mirrors to be polished to a very
aspheric shape. The LBT primaries and secondaries will be among the
most aspheric primaries and secondaries ever made. Burge et. al. 6
describe the null correctors used to test these mirrors. Anderson
et. al. 7 summarize the polishing of a 3.5 m F/1.5
and two 3.5 m F/1.75 mirrors all to a surface accuracy of 16 -- 20 nm
rms.
2.3. F/15 Infrared
LBT is not unique among large telescope projects in wanting to
achieve good performance in the thermal infrared. The infrared
optical design was recently changed to be an F/15 Gregorian focus with
only 0.89 meter obscuration on the 8.4 meter primary. This is the
smallest fractional obscuration of any large telescope. The change to
Gregorian optics was principally motivated to allow us to gain maximum
benefit from an adaptive secondary which can be tested independently
from the primary. All of the wide field optical configuration is
arranged to swing out of the beam when not in use to avoid
contaminating the thermal infrared beam. The secondary is made
sufficiently undersize to account for a 4 arcminute field-of-view, for
±0.7 mm of centration error and diffraction from the edge of the
secondary at thermal infrared wavelengths. The undersized Gregorian
secondary which gives an F/15 beam from an F/14.7 parent is 87 cm in
diameter.

2.4. Interferometry
The binocular mounting of the two 8.4 meter LBT primaries
gives us an interferometric baseline for diffraction of 22.8 meters.
Because the two telescopes track on a common mount, we are able to
bring a field-of-view several arcminutes in diameter to the combined
focus. The experience of the MMT (6 mirrors) has taught us that
phasing a large multiple mirror telescope is possible. The challenge
for LBT has been preserving a low-vibration, low-emissivity, phased
field while allowing (and not compromising) other observing modes in
the telescope. A major activity in recent months has been designing
the appropriate relay optics to bring together the two images at a
combined focal plane. This exercise involves designing an instrument
and a telescope simultaneously. We anticipate that a stable, phased
field combined with developments in adaptive optics will yield
significant observational benefits. Additional discussion of the
interferometric optics is provided by Hill8 and by Byard and
Bonaccini9.

2.5. Wide Field F/4
Inspired by the previous work of Epps, Bonaccini has designed
a 3-element refractive corrector which provides excellent images over
a 1.0 degree field-of-view. The F/4 corrected focal plane will be
used mainly for multiobject spectroscopy, but the inner 30 arcminutes
are optimized for imaging as well. F/4 provides a good match to fiber
optics and to the size of CCD pixels. We have recently switched to
the trapped focus configuration to increase the field-of-view while
decreasing the focal ratio and avoiding conflict with the infrared
focus over the hole in the primary. The wide field Cassegrain secondaries
are 1.3 m in diameter.

3. Telescope Structure
3.1 Structural Requirements
The prime requirement on the structure is that of accommodating on the
same mount the two primary mirrors, the baseline optical
configurations and the corresponding focal stations described above.
These focal stations include: a phased combined focus, two direct
Gregorian foci, two bent Gregorian foci and two trapped wide field
foci. The provisions for a possible future implementation of a
quasi-coudè focus and two prime foci are included in the design.
A second requirement that had a large impact on the telescope design
is that of providing the possibility of switching among all foci and
configurations during the night in a short time. The solution that was
recently adopted, based on swing arms to exchange secondary mirrors,
brought a significant evolution of the telescope design.
A third important requirement is that of handling mirrors and cells to
install them in the telescope. This affected the cell design and also
the telescope geometry because of the need to provide access for large
equipment either to remove and replace the mirrors or for removal and
replacement of the coating. We have chosen to strip and aluminize the
mirrors on-board the telescope since that appears more practical than
removing the mirrors to a remote location.
|
Telescope locked rotor frequency (goal, both axes) | > 8 Hz |
| Optical path difference due to vibrations (>8Hz) | < 0.025 µ m |
| Maximum angular speed (both axes) | 1.5 deg sec -1 |
| Maximum angular acceleration | 0.3deg sec-2 |
| Short term tracking specification | 0.03 arcsec rms |
| Whole sky pointing specification | 0.3 arcsec rms |
| Wind speed for pointing and tracking specification | 24 km hour-1 |
| Maximum operating wind speed | 80 km hour-1 |
Table 1: Telescope Performance Specifications.
Further specifications of more quantitative nature are reported in Table 1.
The resonant frequency specification is of fundamental
importance for the mechanical design of the structure and for the
selection of the type of drives. Setting the locked rotor frequency at
8 Hz requires that the very large structure loaded with all the
accessory parts has all vibration modes (that can be excited by the
drives) above 8 Hz and that all the elements transmitting the motion
are rigid enough not to degrade this performance below 8 Hz.
The vibration specification is a reminder of the interferometric use
of the telescope and therefore of the care that must be taken at all
levels in the design to avoid excitation of local or global
vibrations, while all the other specifications affect primarily the
dimensioning of drives and encoders.
3.2. Function of the Structure
The present telescope design is a descendant of that proposed by
Davison 10. The mount has undergone a great deal of optimization and
tuning over the years; see for example Del~Vecchio et al.11.
This design has shown to provide better global performance than a
number of alternative structural concepts that have been considered.
The 325 ton (including optics and instruments) elevation structure is
supported by two large rolling sectors of 14 m diameter, which rotate
on four radial hydraulic supports and are laterally constrained by two
pairs of hydraulic supports acting on the edges of each sector. The
100 ton azimuth platform is a simple frame that connects the elevation
supports to the four vertical azimuth supports acting on a rail with
14 m external diameter. The azimuth platform is radially constrained
by a central bearing. The main mechanical advantages of this geometry
are in the direct transmission of the loads from the mirror cells to
the elevation platform to the azimuth rail and in the large diameters
available for the drives and for the encoders. The primary mirror
cells and the swing arms supporting secondary and tertiary mirrors are
directly connected to the vertical rolling sectors that are the
stiffest parts of the elevation structure. The motivation behind
swing arm spiders supported from only one end is discussed in more
detail by Del Vecchio, Miglietta and Davison 12. The swing arm
spiders combined with the central concentration of mass in the
elevation structure provide a 2 Hz increase in resonant frequency
compared to the previous superstructure supporting the spiders from
both ends. Compared with previous ``closed'' structures, the open
elevation structure also reduces the cross section for the wind and
the thermal mass of the telescope.
View Figure 6 here
The results of a number of finite element studies of the telescope
structure are described by Del~Vecchio, Miglietta and Davison 12 .
The simple summary is that we are able to achieve locked rotor
resonant frequencies above 9 Hz. The pinion and gear drives, with
four pinions directly driven by torque motors for both azimuth and
elevation axis, were selected for the high rigidity, for
reproducibility and for the simple implementation of the safety
equipment. Because the drive acts at a 7 meter radius and has a
simple and stiff transmission it reduces by only about one Hertz the
resonant frequencies of a telescope structure with ~10 Hz lowest
frequency. Commercially available strip encoders can provide the
required resolution (0.01 arcsec) on 7 m radius.
3.3. Thermal Aspects
The whole surface of the telescope must track very closely the
temperature of ambient air to minimize local seeing. This
requirement dictated a number of measures in the present design of the
telescope. We have adopted four basic strategies: thin structural sections,
natural air circulation, forced heat removal using ambient air and emissivity
control.
All structural elements, with the exception of the vertical rolling
sectors and of most of the azimuth platform, have wall thickness of
less than 10 mm if exposed to ambient air only on one face (20 mm if
both faces are exposed). This maintains the thermal time constant
shorter than about one hour even in very low wind conditions. The
elevation sectors and the azimuth platform, that need substantially
thicker elements, will be shielded from contact with ambient air to
avoid thermal pollution. Rather than using simple thermal insulation,
that would bring a large temperature difference between the massive
and insulated parts and the rest of the structure, we adopted a
``stealth'' scheme based on the combination of insulation and forced
ventilation. A lightweight perforated wall surrounds the massive parts
of the telescope. Ambient air will be sucked through the perforated
wall and will come in thermal contact with the structural parts of the
telescope. The perforated surface will only be subject to a modest
heat load (a few tens of W m -2) and thermalized by an air flow
of typically 100 l s -1 m -2 . This results in a maximum
temperature difference between air and the perforated skin of about
0.2 C °. The corresponding relatively large air flow, about 50
m 3 s -1 , is used to thermalize the massive parts of the
structure, about 200 tons of steel. We expect these to track ambient
temperature with a thermal time constant of about one hour and that a
typical temperature difference of less than one degree could be
maintained in most circumstances. The modest temperature difference
between parts of the structure with different thermal time constant
reduces the thermal deformations, that are difficult to model, and
therefore increases pathlength stability and the pointing and tracking
performance obtainable with open-loop modeling. The thermally
contaminated air will be dumped outside away from the telescope.
Other measures foreseen for the thermal control of the telescope are:
removal of the heat that is produced locally by motors and
electronics, pre-cooling of the hydraulic fluid of the telescope
supports and reduction of the radiative losses of the structure by
covering it with low emissivity aluminum tape. Similar precautions are
taken for the enclosure as described by Salinari and Hill 13 .
3.4. Aluminization
In order to avoid the risk and expense of annually removing the
primary mirrors from the telescope for recoating, we have elected to
strip and recoat the LBT mirrors in their cells on the telescope.
This requires us to make the primary mirror cells compatible with the
rough vacuum behind the mirrors. An external bell jar is put in place
to create the clean (1 microTorr) vacuum needed in front of the
mirrors for evaporation of aluminum. Our coating strategy for
obtaining maximum scientific results includes designing a facility
with the capability to produce coatings with: high reflectivity, low
emissivity and uniform thickness. To further enhance performance in
the telescope we will implement a plan of regular cleaning with CO 2
snow, careful maintenance and protection from the weather. Our design
studies in this area have not found any special problems associated
with aluminizing the mirrors on the telescope or with handling the
bell jar. Rather, the challenges come from applying a high
reflectivity coating on such a large surface and from applying a
uniform coating using a relatively compact bell jar. Atwood and
Sabol14 describe the results of some experimental studies.
4. Summary
- optical configuration ............ binocular 8.4 meter apertures
- equivalent aperture ............ 11.8 meters (2 *55 m 2)
- interferometric baseline ............ 22.8 meters
- resolution (
/ D) in the visible ............ 5 milliarcsec
- primary mirrors ............ 8.4 meter F/1.14 borosilicate honeycomb
- world's most powerful common mount telescope
- consortium partners:
- University of Arizona (25%)
- Italy --- Osservatorio Astrofisico di Arcetri (25%)
- Research Corporation (12.5%)
- Ohio State University (4%)
- mounting type ............ dual ring platform (altitude -- azimuth)
- moving mass ............ 420 metric tons
- site ............ Mt. Graham, Arizona (Emerald Peak, 3190 m)
5. Acknowledgements
Drawings of the telescope structure shown here were supplied by ADS Italia,
of Lecco, Italy. We thank Warren Davison, Roger Angel and Walter Gallieni
for many years of valuable discussions about the telescope design.
6. References
- Hill, J. M. 1990,
``Optical Design, Error Budget and Specifications for the Columbus Project
Telescope'',
S.P.I.E, 1236, pp. 86-107.
- Olbert, B., Angel, J. R. P., Hill, J. M. and Hinman, S. F. 1994,
``Casting 6.5 meter mirrors for the MMT Conversion and Magellan'',
S.P.I.E., 2199 (These proceedings).
- Parodi G., Hill J. M. and Salinari P. 1992,
``Supporting the 8.4m honeycomb mirrors of Columbus'',
Proceedings of the ESO Conference on Progress in Telescope and
Instrumentation Technologies, ed. M.-H. Ulrich, (Garching:ESO),
pp. 301-306.
- Gray, P. M., Hill, J. M., Davison, W. B., Callahan,
S. P. and Williams, J. T. 1994,
``Support of large borosilicate honeycomb mirrors'',
S.P.I.E., 2199 (These proceedings).
- Martin, H. M., Davison, W. B., DeRigne, S. T., Hill, J. M.,
Hille, B. B. and Trebisky, T. J. 1994,
``Active supports and force optimization for a 3.5-m honeycomb sandwich
mirror'',
S.P.I.E., 2199 (These proceedings).
- Burge, J. H., Anderson, D. S., Ketelsen, D. A. and West S. C. 1994,
``Null test optics for the MMT and Magellan 6.5-m f/1.25 primary mirrors'',
S.P.I.E., 2199 (These proceedings).
- Anderson, D., Burge, J., Ketelsen, D., Martin, B., West, S.,
Poczulp, G., Richardson, J. and Wong, W. 1993,
``Fabrication and testing of the 3.5 m, f/1.75 WIYN primary mirror'',
S.P.I.E., 1994, pp. 193-207.
- Hill, J. M. 1994,
``Strategy for interferometry with the Large Binocular Telescope'',
S.P.I.E., 2200 (Companion proceedings).
- Byard, P. and Bonaccini, D. 1994,
``Optical design for interferometry with the Large Binocular Telescope'',
S.P.I.E., 2200 (Companion proceedings).
- Davison, W. B. 1987,
``Structural innovations in the Columbus Project:
an 11.3 meter optical telescope'',
S.P.I.E., 748, pp. 31-37.
- Del Vecchio, C., Davison, W., Hill, J. M. and Gatti, R. 1992,
``Finite element analysis of the Columbus Telescope Project elevation
structure'', Proceedings of the ESO Conference on Progress in
Telescope and Instrumentation Technologies, ed. M.-H. Ulrich,
(Garching:ESO), pp. 79-82.
- Del Vecchio, C., Miglietta, L. and Davison, W. B. 1994,
``Mechanical Design of the Large Binocular Telescope'',
S.P.I.E., 2199 (These proceedings).
- Salinari, P. and Hill, J. M. 1994,
``Enclosure of the Large Binocular Telescope'',
S.P.I.E., 2199 (These proceedings).
- Atwood, B. and Sabol, B. A. 1992,
``Studies of some aspects of aluminizing large astronomical mirrors'',
Proceedings of the ESO Conference on Progress in
Telescope and Instrumentation Technologies, ed. M.-H. Ulrich,
(Garching:ESO), pp. 265-268.