Summary of July 1992
Columbus Project Engineering Meeting
J. M. Hill, Steward Observatory
Columbus Project Technical Memo
UA-92-02
September 11, 1992
http://medusa.as.arizona.edu/lbtwww/tech/ua9202.htm
Abstract
1. Introduction
2. Executive Summary
3. Technical Summary
4. Administrative Summary
5 Post Meeting Progress
List of Figures:

Abstract
This memo reviews the discussions of the Columbus Project Engineering
meeting held in Arcetri during July 1992. This meeting focussed on
getting the detailed design moving again after a year of thinking and
searching for partners. The four main optical issues discussed were:
whether to install an adaptive F/15 secondary for first light; whether
to use a Cassegrain or Gregorian optical design at F/15; whether to
modify the wide field focus to be F/4 at a location above the primary;
and whether to reimage the F/15 bent Cass foci for interferometric
beam combination. A revised mechanical concept for the telescope was
presented. The upper superstructure has been concentrated near the
center of the telescope and secondaries are exchanged with swingarms
rather than trolleys. The enclosure concept is evolving from handling
with an elevator to handling with an overhead crane. Results of testing the
prototype primary mirror supports were presented.
1. Introduction
This memo summarizes the results of the Columbus Project Engineering
meeting which was held in Arcetri on 14--18 July 1992. This was the
first official engineering meeting since April 1991, although there
was considerable technical and political activity in the intervening
months. This memo will highlight the technical results and
discussions of the meeting, but it surely will not do justice to the
atmosphere. Sometimes the small conference room had 15 people having
discussions simultaneously in three different languages. I have taken
some editorial license to make the discussion more coherent and
complete than it may have been at the meeting.
1.1 Project Status
Since the official withdrawal of Ohio State from the project in
September 1991, many engineering activities (and the schedule) have
been delayed. The project has been revitalized with the addition of
Research Corporation as a third partner in June 1992. Approximately
$40M of funding is thereby available to build a stripped-down one-eyed
version of the telescope. Primarily to avoid confusion, this
discussion will assume that we intend to build the full two-shooter
with instrumentation over a period of several years.
1.2 Background
Baseline Design
The present (1991) baseline telescope design is a pair of 8.408 meter
diameter mirrors with 14.408 meters between centers. This telescope
will have wide field optical secondaries (on trolleys) and 3 element
refractive correctors to give a 50 arcminute field at F/5.4. The IR
Cassegrain secondaries optimized for the thermal infrared at F/15 will
be mounted in a flip-top arrangement with F/33 secondaries for
combining the beams from the two telescopes. The combined focus will
occur with only 4 reflections to the center of the telescope. The
Cassegrain focal stations will have at least one and possibly two
locations for mounting a bent Cassegrain instrument. The combined
focus will have an unimplemented provision for a coude combined focal
station with 6 reflections to a gravity stable focus below the
telescope. The tertiaries will also be mounted on trolleys for rapid
interchange.
Optical problems
In pondering the telescope and instrumentation for the last year, we
have identified the following ``problems'' with the baseline concept.
(Note that ``problems'' means ``lack of perfection'' more than it means
``things that won't work''. The previous design was a perfectly
workable telescope, but an unexpected year to think has brought some
new insight.)
- ``Nobody''* wants to use the Bent Cassegrain focal stations.
For each type of instrument that might mount at Bent Cass, there is
some reason why direct Cassegrain will give better performance. These
reasons include: induced telescope polarization, lower throughput from
a third reflection, a smaller field restricted by tertiary size, more
scattered light from the additional surface, higher infrared thermal
background, and a more restricted instrument mount. At some level
this is a psychological issue since some other telescope projects have
chosen only to work at a Nasmyth focus with three reflections. The
major argument in favor of the Bent Cass is to provide a quickly
accessible backup or optional instrument to maximize the efficiency and
flexibility of the telescope under changing conditions. (* Nobody does not include
sub-millimeter observers.)
- A tertiary large enough to feed a substantial (any) F/5 wide
field to Bent Cass introduces unacceptable central obstruction at F/15
and F/33. This leads naturally to a two tertiary concept with the
resulting hardware and optical complexity or cost.
- In addition to the three baseline secondary pairs at F/5.2,
F/15 and F/33. It is clear that many projects (i.e. long slit spectrograph)
would benefit from an additional pair of F/15 secondaries equipped for
an extended (10 arcmin) optical field. This introduces additional cost and
exchange complexity, but could save substantial instrument money. The F/15
secondary would nominally have only a small unvignetted field and an
IR selected coating (Ag or Au).
- What we perceive as the two most heavily used focal stations:
wide field F/5 and IR optimized F/15 have the problem that the Wide Field
Corrector in the Cass hole prevents the observer from switching between these
two configurations during the night. Rapid changeovers can only occur
between direct cass and bent Cass or combined focus.
- Rapid advances in active and adaptive optics technology means that
we must continually re-evaluate our strategy in this area. This could
significantly impact our selection of preferred focal stations. In fact the
question arose as to whether it was even worth building a non-adaptive
F/15 secondary (even the baseline secondaries are already active). Some
uses of the combined focus would like to have an additional real pupil
to place an adaptive element. As another example, the flip-top secondary
exchange between F/15 and F/33 would make it more difficult to place
the feed mirror for a laser guide star behind the secondary.
Mechanical problems
On the mechanical side there were four similar objections:
- The handling of mirrors and equipment around the telescope
was to be done with trolleys on the telescope and a large elevator on
(outside) the enclosure. Initial engineering suggested that this was
a rather expensive solution (corollary: all handling of 8m mirrors is
expensive.).
- The classic Columbus telescope had an impressive
superstructure to hold the secondary mirrors and beam combiners in
place. An ideal telescope would not want to have all this metal out
there in the wind around the incoming beam.
- Since the change of primary diameter from 8.0 to 8.4 meters,
we had been unable to get the elevation structure resonant frequency
back above 9 Hz.
- Stiffness of the secondary spider attachment points continues to
be a difficult issue (true for all designs).
1.3 Agenda and Attendees
| Monday July 13 | Adaptive Mirrors and Spider Diffraction |
| Tuesday July 14 | Discussion of Optical Design Options |
| Wednesday July 15 | Summary of Mirror Support and Handling
Review of Jet Ejectors and Mirror Ventilation |
| Thursday July 16 | Mirror Cells, Actuators and Hardpoints |
| Friday July 17 | Telescope Structure, Spiders and Focal Stations
Enclosure and Handling Options |
| Saturday July 18 | Review and Discussion |
| Monday July 20 | Meeting Summary and Planning |
The following people attended at least some part of the meeting:
| Franco Pacini | Arcetri | |
Piero Salinari | Arcetri |
|
Luciano Miglietta | Arcetri |
|
John Hill | Arizona |
|
Roger Angel | Arizona |
|
Irene Cruz-Gonzales | Mexico |
|
Warren Davison | Arizona |
|
Shawn Callahan | MMTO |
|
Tom O'Brien | Ohio State |
|
Domenico Bonaccini | Arcetri |
|
Ciro DelVecchio | Arcetri |
|
Giancarlo Parodi | BCV |
|
Elfego Ruiz | Mexico |
|
Luis Salas | Mexico |
|
Salvador Cuevas | Mexico |
|
Bruno Marano | Bologna |
|
Walter Gallieni | ADS |
|
Riccardo Gatti | ADS |
|
Rafaele Tomelleri | ADS |
|
Bruce Atwood | Ohio State |
2. Executive Summary
The following table is a one page summary of what was ``decided'' at the
Columbus Engineering meeting. Many of the options and motivations are
discussed in more detail in the next section. The first column is
the current choice to include in the baseline design. The second column
indicates a fallback option if the first option should prove undesirable.
| FIRST CHOICE | BACKUP PLAN |
|
Rigid F/15 Secondary at First Light | Direct Implementation of Adaptive M2 |
|
Short (above M1) F/4 Wide Field | Old F/5 Cassegrain Wide Field |
|
Gregorian F/15 Secondary (concave) | Cassegrain F/15 Secondary (convex) |
|
5-mirror Reimaged Beam Combiner | 4-mirror Direct Beam Combiner |
|
New Telescope Structure | Classic Telescope Structure |
|
Swing arm M2 Exchange | Trolley M2 Exchange |
|
Crane Handling | Elevator Handling |
|
Screw plus Spring Hardpoints | Chain plus Spring Hardpoints |
|
Pneumatic Cylinder Actuators | --- |
|
Separate Washing and Aluminizing | Combined Aluminizing Villa |
|
Telescope ``Cellar'' Entrance | Ground Level Entrance |
|
F/15 Tertiary Only | Small Field F/5 Tertiary |
|
Wind-Compensated Mirror Ventilation | --- |
The meanings of these cryptic decisions are discussed later in this memo.
3. Technical Summary
3.1 Optics
3.1.1 Should first light have an adaptive F/15 secondary?
Pro:
- By 1998, nearly every instrument will benefit from the
addition of a ~ 100 element adaptive mirror at F/15. Such an
adaptive mirror would allow the telescope to be diffraction limited
most of the time at 2 microns.
- If adaptive secondaries are in common use, the newly
fabricated rigid secondary will quickly become obsolete.
- The secondary is a very efficient place to locate the adaptive
mirror, since no additional optical surfaces are required and all
instruments can take advantage of it.
- A permanent adaptive secondary would drastically alter the
specifications on many of the instruments.
- It would be technically attractive for many scientists and engineers
to develop this secondary.
Con:
- Developing the adaptive secondary will add additional costs to
the early phases of the project.
- Relying on a new adaptive secondary for telescope testing and debugging
would place the telescope schedule at risk.
- We are already late in starting the adaptive program,
if we want a secondary by first light.
- The precise direction of the adaptive mirror design is not clear
at the present time.
- A much simpler tip-tilt system will already achieve the diffraction
limit at 10 microns.
Result:
The Project Office has decided not to pursue an adaptive
secondary for first light. At least one rigid (non-adaptive) mirror
will be fabricated. But we strongly endorse the development of an
adaptive secondary for implementation as early as possible in the life
of the telescope. (no change from previous plan)
Adaptive Optics Strategy
The following is a summary of the Columbus Project adaptive optics philosophy
extracted from an email message a few weeks before the engineering meeting.
- Columbus will take full advantage of adaptive optics in both
Cassegrain (or Gregorian) and Interferometric mode. All aspects of
the telescope design have attempted to take this into account ---
starting with producing the best possible image w/o adaptive
correction and with very clean infrared focal planes.
- Adaptive secondaries are being planned to minimize the number of
optical surfaces in the optical train, and to make the corrected focal
plane available to as many instruments as possible. (That doesn't
mean we are ignoring the possibility of making reimaged pupils.)
- Active optics is completely integrated into the baseline design.
Active in this context includes primary figure control, coarse
wavefront analysis, active alignment and focus of the secondary
mirror, and rapid (tip-tilt) guiding. (These are all budgeted
separately from the $2M for adaptive secondaries. So the total budget
for all the active and adaptive systems is more like $4M out of the
total $60M (1989$)).
The official Columbus budget has a line item of $2M for a pair of
adaptive secondaries. This was an arbitrary decision made in 1989
intended to be a strategy decision rather than a technical design.
Because the technology is changing so rapidly it is still difficult to
say exactly what form these secondaries will take. We want the
initial adaptive system to work over a broad wavelength range --- say
1 to 10 microns. The capabilities will clearly evolve over the
lifetime of the telescope.
3.1.2 Should the F/15 Secondary be Cassegrain or Gregorian?
Pro:
- A Gregorian adaptive secondary would be conjugate to a layer
in the atmosphere 100 meters above the telescope rather than the
Cassegrain conjugate 100 meters below the telescope (below prime
focus). This would allow a factor of perhaps 3 increase in the
effective isoplanatic angle for seeing just above the telescope;
thereby increasing the adaptively corrected field-of-view.
(``conjugate'' in this context means the reverse image of the
secondary formed by the primary.)
- A concave Gregorian secondary which is ellipsoidal is much easier to
test during figuring since it does not require a Hindle sphere or a null
corrector. This might mean a 50% reduction in cost.
- The Gregorian secondary allows access to prime focus for artificial
stars or polarizing elements or occulting disks.
- Because of the F/1.14 primary, the Gregorian makes only a minimal
increase in the length of the telescope. The secondary is 1.8 m higher,
but the spider fits on the old telescope structure.
- The primary is easier to bend into an aplanatic ellipsoid
by using a tension band around the edge of the mirror (compared to an
anti-tension band to bend the RC hyperboloid).
- If we adopt the wide field F/4 focus, then the Gregorian secondary
swings over the smaller wide field secondary. This simplifies the swingarm
design.
- The Gregorian secondary may permit innovative instrument designs such
as the wide field refractive collimator being pursued by Shectman.
Con:
View Figure 1 here
3.1.3 Should we use reimaged beam combination?
Pro:
- A reimaging beam combiner would allow us to eliminate the F/33
secondary and the flip-top exchange by using the F/15 secondary to
feed the combined focus.
- A reimaging beam combiner allows the creation of a real pupil image
where additional adaptive elements could be placed.
- A common F/15 secondary reduces the number of adaptive secondaries
that would be needed.
Con:
- More than the minimum 4 mirrors in the combined focus would increase
the emissivity in the thermal IR unless cooled optics were used after the
tertiary.
- Can the reimaged beam combiners really deliver enough unvignetted
field at the required image quality?
Result:
A reimaged beam combiner is being designed. See the future memo on
beam combiners for all the gory details and specifications.
View Figure 2 here
3.1.4 Move wide field focus above the primary?
The question is whether to change the wide field F/5.4 corrected
focus at Cass to a F/4.3 corrected focus about 4 meters above the primary.
Specialized multifiber instruments and a wide-field CCD imager would be used
at this focus.
Pro:
- Moving the focus higher will remove the 3-element refractive corrector
from the central hole. Thus, enabling more rapid changeover from
wide field optical to F/15 infrared work.
- Moving the focus higher will make the 1.9 meter secondary much
smaller and much less expensive (1.2 -- 1.3 m).
- F/4 is a better match to CCD pixels for imaging.
- F/4 is a better match to fiber focal ratios for spectroscopy.
- By moving the corrector out of the central hole, we can decrease
the hole size slightly (to match the MMT/Magellan hole diameter at 0.89 m).
This reduces the central obscuration for the F/15 focus.
- If optical design permits, we can expand the field without worrying
about the diameter of the central hole.
- For a fixed field angle, the size of the corrector elements is reduced.
- The platescale matches the corrector on the MMT Conversion F/5 focus.
Con:
- The short ``trapped'' focus may actually increase the central
obscuration in the converging cone rather than at the secondary
baffle. The central obstruction of the ``old'' F/5 corrector was
approximately 2.6 meters (from the secondary baffle).
- The observer access to the wide field instrument would be greatly
inhibited by being above the primary.
- A very compact and specialized instrument rotator is required.
- Maybe the same excellent image quality cannot be achieved.
- Lack of an accessible naked Cassegrain focal station might
reduce flexibility or make it difficult to design high-throughput ultraviolet
instruments.
- A smaller instrument envelope is available (comparable to that
on the MMT Conversion).
View Figure 3 here
Result:
We will explore the optical and mechanical design possibilities
and give it a try. The following acceptance criteria have been laid out
for the trapped F/4 focus: (These are not the full corrector specifications.)
- Field diameter remains at least 50 arcminutes or increases to
near 1 degree.
- Polychromatic image quality is at least 80% encircled energy in
0.5 arcsec over 90% of the field.
- The central obscuration of the telescope does not increase beyond 3.2 m.
- Instrument diameter can be at least 2.0 meters.
- Instrument height can be at least 2.0 meters (above tertiary?).
- The inner 30 arcminutes of the field has broadband images with 80%
encircled energy in 0.25 arcsec diameter.
- Not more than one asphere is permitted.
View Figure 4 here
3.1.5 Other Optical Discussions
Wide Field Correctors
Domenico Bonaccini reviewed the work on wide field correctors
in the normal Cassegrain position. Good solutions exist for both
all-spherical and single aspheric designs. The images are excellent
out to 44 arcminutes in the all-spherical version. The good field
increases to 52 arcminutes by adding 1 asphere. Domenico has alsodemonstrated that the ADC can be placed after the third element to
allow it to be ``easily'' removed for programs which do not need it.
Domenico will provide details in a future technical memo.
ADC glasses are a perennial topic of discussion. We discussed
the possibility of dividing the wavelength range that the ADC had to
cover to permit the use of glasses with higher UV transmission. The
idea would be to have a ``deep UV'' ADC covering 310 nm to 4000 nm and
a ``blue'' ADC covering 350 nm to 1000 nm. Detailed study of the
glasses is required to see if there is a practical breakpoint. (This
sort of detail will be resolved after we freeze the global dimensions
of the telescope and the corrector.)
We also discussed the possibility of putting the wide-field
corrector only at the bent Cassegrain focus. The cost of a 1.9
meter (major-axis) flat tertiary makes this configuration
unattractive.
Adaptive Correction
There was a brief discussion of how much active and/or
adaptive correction is required in various situations. The adaptive
optics group at Arcetri (Bonaccini, Brusa, Esposito, Strauss) has been
modelling the atmosphere to compare things like centroid tip-tilt vs.
brightest speckle tip-tilt. These models will be used to set
specifications on various parts of the telescope system.
3.1.6 Interchange
At the present time, the ``old'' Columbus baseline has six optics
movement mechanisms per 8 meter ``barrel''. These are:
- wide-field secondary in/out
- narrow-field secondary in/out
- narrow-field secondary flip, and
- tertiary flat in/out
- tertiary rotation in the plane of the primary
- tertiary rotation varying the beam inclination
These changes could happen in 10 -- 15 minutes during the night. Other
changes involving the instruments or the wide field corrector would
occur in the daytime.
It is suggested that these movements might be reduced to four while increasing
versatility.
- The wide-field secondary, its baffles, field corrector and either a
fiber table of an imaging detector package should all be carried in
or out of the beam in a single movement by mounting these at an
Epps focus.
- Narrow field secondaries would be used ONLY at the
Gregorian position. They would be carried into place by a single
mechanism with three positions at 120 degrees, position 1 in,
position 2 in, and position 3, both out of the beam for aluminizing.
In this, position 1 is intended to be a mount into which one could
place a mirror cell with assorted actuators, or a prime focus device,
and position 2 is a similar fixture.
This mechanism should not be expected to carry secondaries of
larger than, say 80 cm in diameter, which would restrict Cassegrain
focal ratios to F/17 or slower Then it would be less than 1m. above
the prime focus, and so also capable of carrying lightweight prime
focus equipment.
- Tertiary in or out. This tertiary would serve both to provide bent
Cass foci and to serve the combined focus.
- Tertiary rotation around the axis of the primary. to feed
combined foci, and one or more bent Cass positions. It would seem
that a single angle of inclination to the primary axis should allow
enough versatility (depends on beam combiner design).
(This discussion on interchanges was extracted from a longer memo by
N. J. Woolf on telescope versatility. It succinctly describes the
philosophy of the discussions at the engineering meeting.)
3.2 Mirror Support and Handling
In a separate memo, Giancarlo Parodi briefly summarizes the results of
the 13 BCV Reports produced since the previous engineering meeting.
These reports dealt primarily with the topics of local stresses, mirror
handling, revisions of axial and lateral forces, and active correction
of aberrations. A summary is provided in Columbus Tech Memo OAA-92-01.
3.2.1 Future Work
Local Models
The highest priority task is to build another detailed local model
to evaluate the stress over the support pads. This is important so we can
freeze the design of the load spreaders and actuators with appropriate limits
on the push and pull forces. This model will include the local fillets
as well as the load spreader interface. It will also be improved by adding
displacement boundary conditions from the global model.
8.4 meter Handling
There is still some work to do on lifting and handling the 8.4 m mirror
and mold material since the stresses are still about 20% too high.
Methods to reduce the stress include: redistributing the forces, removing
the hextiles, changing the pattern of pads. The model will also be updated
to better estimate the shear stiffness of the backplate and to better
estimate the stress concentration at the backplate holes.
A parabolic temperature gradient appropriate to annealing will also be added
to the list of calculated cases.
This work on handling analysis will be delayed until we have the results
of lifting and cleaning the 6.5 meter mirror.
Final Optimization
The ``final'' optimization of axial and lateral force distributions will
need to be done again since several of the actuators (L12 and L35) are
blocked by the hardpoints. The re-optimization will also be needed if we
change the central hole diameter.
Automatic Stress Verification
We discussed the need for long-term documentation of these stress analysis
results. How will the Columbus engineer in 2035 know how to safely
lift the primary mirror? Is it practical to develop a general computer
model that can answer this sort of question with specific results?
In any event, we will need to produce a detailed manual.
We also discussed methods for detecting when the mirror cell control
system wants to apply pathological force distributions to the mirror.
For example, pushing with all the actuators near the edge and pulling in the
center could be very dangerous.
Aberration Corrections
Using axial correction forces only, we can change the conic constant
by 3 microns p-v (without degrading the figure or overstressing the
glass). Additional correction of the conic constant can be achieved
by using a tension ring around the outside edge of the mirror.
(Moving the focal plane a meter requires 26 microns of spherical
aberration, so this adjustment is mostly useful for tuning out
fabrication uncertainties.)
Additional calculations of active correction forces will be low priority
until some of the more pressing design jobs are completed.
= 50°
and
= 15°.
Attachments
Despite being more difficult to fit into the actuator pattern, we are
going to use some sort of modified loadspreader to attach the hardpoints
to the mirror backplate. There is too much moment for a single puck
attachment to handle. The larger attachment area also provides more
stiffness from the RTV bond and allows a larger safe breakaway force
for the hardpoints.
Design
Rafaele Tomelleri presented a preliminary design for a hardpoint mechanism.
Unlike the historical concept, this design separates the motion from the
breakaway function. Position adjustment is provided by a motorized screw.
Breakaway under an unexpected force is accomplished by a pair of spring
loaded plates. Load cell stiffness is increased by building the load cell
into a lever arrangement that increases the effective stiffness by the
square of the mechanical advantage while decreasing the apparent sensitivity
by the first power of the mechanical advantage.
Assuming that the fulcrum and the support arms are infinitely stiff,
the load cell deflection is given by P * X -1 * K-1L where
P is the total load, X is the mechanical advantage and KL is the
load cell stiffness. Because the fulcrum side doesn't deflect, the
central deflection is given by P * X -2 * K-1L
and therefore
the central stiffness, KT, is given by X2 * KL. Because we were selecting the load cell for stiffness rather than sensitivity, the loss
of sensitivity should not be a problem unless the mechanism is prone to
drift.
Tomelleri will complete the prototype design. Changes include shifting
one of the pivots to the center-of-mass to avoid lateral moments on the
mirror (We missed that one in the original specs.). We have also
increased the target stiffness to 200 N/ µ m for the mechanism and
100 N/µ m for the stack from the glue joint to the mirror cell
attachment. This is to give the mirror a higher resonant frequency in the
cell. Additional design details will be included in a future ADS report.
Later in the year, a prototype hardpoint actuator will be constructed
and tested. A piezo-based servo loop closed around the load cell
reading may be used if we wish to increase the stiffness beyond the
levels described above.
View Figure 5 here
3.3.3 Mirror Support Actuators
The prototype mirror support actuators for MMT and Columbus and Magellan
have been completed and tested. The design includes the earthquake stops
and plans for installation and alignment.
MMT Test Results
Shawn Callahan summarized the results of testing the prototype actuators.
The actuators (revision 57) now meet all of the mechanical requirements.
The test results are described in a separate memo: ``Preliminary performance
test results of the 6.5 meter mirror support actuator design'' --- UA-92-03.
Shawn also showed photos of the 2 m3 mockup of the inside of the mirror
cell.
Mirror Safety
There was a discussion (without definite resolution) of how to prevent the
mirror support system from damaging the mirror by applying certain
pathological force distributions. Individual actuators are designed so
they cannot apply enough force to damage the mirror locally. The obvious
dangerous example is a case where all the axial actuators on the outer
part of the mirror push, while those at the center of the mirror pull.
Clearly, careful design and safeguards will be required in both hardware
and software.
Polishing Cell
Warren Davison described the design of the polishing cell being designed in
Arizona by Roberta McMillan. The Mirror Lab decided to build a polishing
cell specific to the 6.5m mirror to minimize the cost and pain on the
first go-round. The structure of the cell is very similar to the
telescope cell, except that it lacks all the connections to additional
structure. The polishing actuators (axial) are glycerine-filled
cylinders with variable mechanical advantage levers. These allow for
adjustable passive support. A lively discussion followed on whether it
would be possible or even desirable to polish the mirror on active
pnuematic supports like those in the telescope. It might also be possible
to polish on rubber pads and test on the telescope supports.
Telescope Cell
ADS has made a number of drawings of the telescope cell for mirror support.
No problems have been encountered except that this is a very crowded space.
The final design is on hold waiting for sub-assembly details.
View Figure 6 here
3.4 Telescope Structure
3.4.1 ``Nuovo Telescopio'' a.k.a. ``Columbus Lite''
If the ``Columbus Classic'' telescope design had any weak points, one of them
was the large amount of trusswork required to stiffen all the attachment
points around the top of the telescope. In an attempt to reduce the mass
and increase the performance, Arcetri has designed a new telescope which
eliminates much of the trusswork and concentrates the steel in the center
of the telescope. In Italy this design is known as ``nuovo telescopio''
while I have named it ``Columbus Lite'' because it should have ``less
superstructure and better seeing'' (apologies to Miller Brewing). This
telescope design accommodates all the same focal stations and configurations
as the previous one (allowing for the changes made at this meeting). The
significant non-structural change is that secondaries and tertiaries
are interchanged by swingarms rather than trolleys.
View Figure 7 here
3.4.2 Spiders
The thickness of the spider vanes in our ``structural'' spiders is
limited by the local moment-of-inertia required to eliminate buckling
and low frequency local modes (assuming we have already abandoned tensioned
spiders). Piero Salinari has then made the argument that structural
spiders should be one-sided in order to get the maximum moment of inertia
for a given obscuration. Lateral vibrational modes prevent you from
carrying this line of reasoning to a single post. Ciro ``spider man''
DelVecchio has been busy designing spiders that only attach on one
side of the secondary mirror. Cross-braces have been used to keep
the lateral frequencies high. These braces make unusual diffraction
patterns, but the total obscuration seems to be lower than in the old
two-sided designs. Diffraction modelling shows that the Strehl ratio
decreases at twice the rate the obscuration increases. Therefore, a
small decrease in obstruction can easily compensate for a less regular
diffraction pattern. The problem
with the one-sided spiders is that the connection to the telescope
structure becomes more difficult. The spider design effort is an on-going
task while iterating with the overall telescope structure and the optical
design.
View Figure 8 here
3.4.3 Structural Analysis
Riccardo Gatti presented preliminary finite element results of the
revised telescope structure. There are still some problem areas in
the detailed model, but the results seem to confirm that the resonant
frequency is substantially higher (2 -- 3 Hz) than the same mass of
steel in the old model. The lowest eigenfrequency of the elevation
structure was 9.2 Hz and the total elevation mass including mirrors
and instruments was 329 tons.
Several attempts have been made to reduce the radius of the C-rings
from 7 meters to 6 meters. These have not yet been successful, but
there is a possible weight savings of 25 tons if the structure can be
modified in this way.
View Figure 9 here
3.5 Enclosure and Equipment Handling
The enclosure design has changed in several significant ways. First,
the 50 ton elevator which was previously planned for handling mirrors
and spiders and instruments was looking rather expensive. Second, the
revised telescope design no longer permits moving things on trolleys.
Therefore, we have revised the handling concept to use an overhead
crane in concert with the swingarms. The crane will lower things to
the ground through a large (4 x 10 m) hatch in the floor. This hatch
in front of the telescope makes the rotating building deeper, but
allows us to make better structural use of the building end walls.
Changeovers will be simpler to do in bad weather since everything is
inside. The large elevator is removed, but we still retain large
obstructed openings in the end walls for ventilation. The building
will still contain a 2 x 2 m elevator for people and small equipment.
The aluminizing bell jar and coating removal stations will now be two
separate modules that fit through the floor hatch. The ground floor
layout will be revised to accommodate crane handling as well. Roger
Angel has pointed out that the ground floor may actually be below
present mountain grade. The details depend on which site is selected
and how the bedrock looks.
View Figure 10 here
4. Administrative Summary
On Monday July 20, 1992, P. Salinari and J. Hill met to review the
results of the engineering meeting and to evaluate how the technical
aspects of the project stand with respect to the management and
schedule aspects. We reviewed the schedule for the next 9 months as
well as the long term schedule. The long term schedule is equally
paced by the telescope, the enclosure and the primary optics. Some
financial hurdles still remain to be crossed before the detailed
design and construction of the telescope can proceed at maximum pace.
4.1 Optics
Based on the discussions at this meeting, we have set a goal
to finalize and freeze the optical designs for all focal stations by
the end of October 1992. A number of cost and performance tradeoffs
remain to be done, but the overall picture is encouraging from the
perspectives of both cost and performance. The primary mirror
dimensions are completely fixed except for some minor tweakings of the
honeycomb pattern near the edge of the mirror. The three outstanding
optical issues (not counting instruments) are:
- The design (redesign) of the optical wide field focus. This
depends on the performance that can be obtained from the high F/4
corrector compared to the low F/5 corrector.
- The design (redesign) of the interferometric focus. This has to
do with whether a 5-mirror reimaged combined focus can provide
adequate performance to replace the 4-mirror direct beam combination.
- The choice of Gregorian vs. Cassegrain optics for the
infrared-optimized focus at F/15.
Work on these issues is now underway in Arizona, Italy and Ohio.
See the discussion in an earlier section.
4.2 Primary Mirror
The Mirror Lab will cast the Magellan 6.5m mirror in April
1993. The exact schedule for the first Columbus primary mirror remains
slightly uncertain because of possible Gemini 8m commitments by the
Mirror Lab. Prompt funding of either or preferably both projects is
the best way to avoid schedule delays. The only way that Gemini would
adversely affect the Columbus schedule would be to delay a funding
decision into 1993 while still maintaining the third spot in the
queue. If either Gemini or Columbus is able to make a cash commitment
by the end of 1992 (and thereby form a queue), then the Mirror Lab
will be able to proceed in an efficient manner without delay.
4.3 Telescope
The major activity on the telescope design front is to
complete the design of the ``new'' or ``lite'' telescope and the
comparison with the old design. The preliminary results indicate that
the new structure will substantially out perform the old structure
(which was already world-class) without increasing the cost. It
appears that we will gain 2 or 3 Hz in resonant frequency without
increasing the mass. The design of the swing arms to exchange the
secondary and tertiary mirrors still requires considerable attention,
but the early results look good. After the optics have been frozen
and reviewed, we will finalize the telescope design decisions in
November 1992. We expect to have another conceptual review of the
telescope design in Tucson in January 1993. Conceptual review is
somewhat of an understatement since we are already well into the
detailed design of the overall system. We would like to have the
detailed design completed and to select a contractor in the Fall of
1993. This should enable the telescope to be erected in the Fall of
1996. First light would then be in late 1997.
4.4 Enclosure and Site
The enclosure design is well under control, but will not be
completed until all the telescope and handling issues have been
resolved. Our goal is to select an architect and proceed with
detailed design of the enclosure starting in the Spring of 1993. We
also need to obtain Forest Service approval of the detailed site
selection by the Summer of 1993.
4.5 Aluminizing
We are very confident of our conceptual design of the primary
coating systems. We are currently in need of resources to continue
some experiments which are needed before we can complete the detailed
design. Experiments are planned for Bologna and Ohio and Arizona.
4.6 Instruments
Instrumentation development is nearly at a standstill until
the required additional funds and/or partner institutions can be
obtained.
4.7 Budget and Schedule
Our current understanding is that the Columbus Corporation
will be formed in September 1992. On the Arizona side, that should
clear the way for the sale of the bonds to proceed. From the
technical perspective, we need to have substantial cash available in
early 1993 in order to avoid any future schedule slippage. Somewhere
between $3 and 4 million are needed in calendar 1993. Actual cash
rather than simply commitment is required so that we may proceed with
hiring a project manager and an architect and with entering the Mirror
Lab queue. We need approximately $150K in Arizona and $400K in Italy
to complete the tasks planned for calendar 1992 without causing
further schedule delays. Details are provided in the project
schedule, budget and financial plan coordinated by A. Lampis. We
anticipate needing ``duty-free'' legislation by January 1994. The
complete two-shooter can be built most efficiently by having the
funding from the final partner beginning in Spring 1994.
5 Post Meeting Progress
5.1 Optics
This section still has a stream-of-consciousness style --- actually
stream-of-email style. It is intended to be current through the
end of August 1992.
5.1.1 Beam Combination
Everybody and his uncle has been designing 5-mirror beam
combiner layouts. Bruce Atwood and Paul Byard have found a geometric
solution that works, except that it has not (yet) been optimized to
produce acceptable images over a substantial field. Jim Burge found
another similar solution, but the Zemax optimizer choked on it. J.
Hill and R. Angel have been working on codes to attack the problem
analytically.
People didn't object to 5 mirrors, especially if the fourth
and fifth mirrors can be cooled inside a sealed tank. The ``OSU''
solution clearly demonstrates that geometric solutions
are possible. Now we have to decide if we can put in practical
aspheres to create sharp images. I also note that the possible
combiner geometries are seriously limited by reimaging to F/33. A
faster geometry combined with control of focal plane tilt could allow
more flexible placement of the fold flats. Don McCarthy will
think more about the constraints on the combined focal ratio. The
high beam combiner mirrors (currently just below the Gregorian
secondaries) present some structural difficulties, but they need to be
fairly high to get an unvignetted field.
In the five mirror combiner, the height of M5 is limited by the
magnification from f/15 to the final f/ratio, not by the field size or
the crotch height. The best I can do for nominal f/15 focal
position and 2 meters extra for the combined focus is f/25.
The magnification puts the limit on the
beam combiner height. But, the motivation for F/33 was to keep the
tilted focal planes in phase. But since reimaging retilts the focal
planes, that whole constraint has changed. AND, if we assume the exit
pupil hasn't moved (obviously false), then we also need a high beam
combiner to keep 4 or 5 arcminutes of unvignetted field. So now we
should re-evaluate focal plane tilt and vignetting in the reimaged
case.
5.1.2 Wide Field Correctors
Wide Field Corrector) Both Epps and Byard have produced
workable designs near F/4. These are acceptable, but not as good as
Bonaccini's best F/5 result. The Epps version gives 0.3 arcsec rms
image diameters over 50 arcminutes with one aspheric surface. This
gives me confidence that the final solution can be even better. Now
we need someone to layout hardware around these optics and verify that
the corrector plus instrument plus rotator plus spider don't make the
obstruction too large.
This is viewed favorably by everyone with the two caveats:
- that we can optimize the images a little bit better.
- that we can work out a suitable mechanical solution, including
proving human access to the instrument for setup/debugging.
5.1.3 Gregorian F/15
Our thinking seems to be evolving toward taking advantage of
the Gregorian's testability and other operational advantages rather
than its larger isoplanatic patch.